1 - Key Concepts - Dependency Errors.

In this section, we are analyzing some concepts about errors in planning.

Isabela Torres

Last Update vor 9 Monaten

This is an error that occurs primarily because at a workstation, I cannot start a production order if the previous one has not been completed.

The system shows us the errors by drawing a red underline between one process and another, indicating which one(s) have an error.

In Room 21, we have production order 1 and production order 2. The system shows that Order 2 is starting without Order 1 having finished, which is identified as an error because it's not possible to start an operation if the previous one is still in progress.

How to identify the error?

In the top left corner, you have the option to view the errors, where it will show you a list to identify whether it's a dependency error or an overlapping error,

The solution to this is to move Order 1 until Order 2 has finished to avoid errors in the system.

We realize that we don't just have errors in our planner; there is also no red underline between operations

And that's it; with this process, we can avoid dependency errors.